Skyborn secures all major contractors for Gennaker offshore wind farm

  • Written by Telegraph Magazine

HAMBURG, GERMANY - EQS Newswire - 1 September 2025 -

  • Preferred Supply Agreements (PSAs) have been awarded for supply of monopile foundations to EEW Special Pipe Construction GmbH, transition pieces to Dajin Heavy Industry, foundation transportation and installation to Seaway7 and inter-array cable supply and installation to the consortium of Boskalis and TKF.
  • The Gennaker project is securing employment local to the project in the Mecklenburg-Vorpommern region in northeast Germany, where the monopile foundations will be manufactured.
  • Gennaker to add up to 976.5 MW to Germany's renewables capacity*.
Skyborn Renewables (Skyborn) is proud to announce it has secured contractors for all major packages of the Gennaker offshore wind farm. The completion of PSAs signatures during the summer of 2025 is a major step towards the successful completion of Gennaker, planned for 2028.

"We are extremely proud of the agreements we have signed with each of Gennaker's suppliers. We, and the project, can now rely on a pool of highly experienced contractors to deliver Gennaker on budget and on schedule. The signed preferred supplier agreements also demonstrate our commitment to Gennaker being rooted in the local community, delivering long-lasting value and benefits for Mecklenburg-Vorpommern. Offshore wind delivers positive impact on the ground, be that via investments, jobs or decarbonization!" says Patrick Lammers, Skyborn CEO.
"I would like to not only thank our suppliers, but also the Skyborn team, whose dedication and hard work has been key to bringing Gennaker one step closer to reality." Lammers adds.
  • Monopile foundations: Preferred Supply Agreement has been signed with EEW Special Pipe Construction GmbH (EEW SPC) for the supply of 63 monopile foundations, each monopile is up to 54.1 metres long, with a top diameter of 7.5 metres and will weigh up to 877 tonnes. Monopiles will be manufactured in Rostock – only 40 kilometres from the Gennaker site. The contract will further bolster the already strong local Mecklenburg-Vorpommern supply chain through a robust employment plan, securing jobs at EEW SPC which currently employs 1,000 people. A ceremony was held at the EEW Special Pipe Construction premises in Rostock to celebrate this major milestone for the project.
  • Transition piece: Preferred Supply Agreement has been signed with Dajin Heavy Industry for supply of 63 transition pieces. Each transition piece will be approximately 20 metres high and will weigh approximately 400 tonnes. The manufacture of the transition pieces will be performed in Penglai, China and will be finalised in Odense, Denmark.
  • Foundation transportation & installation: Preferred Supply Agreement has been signed with Seaway7 for the transportation and installation of monopiles and transition pieces for the project.
  • Inter-array cables: Preferred Supply Agreement has been signed with the consortium of Boskalis and TKF for the supply and installation of approximately 140 kilometres of inter-array cables. Inter-array cables are to be manufactured in Eemshaven, Netherlands.
These agreements follow prior announcements of Gennaker for turbine supply and long-term service with Siemens Gamesa Renewable Energy and wind turbine transport and installation with Fred. Olsen Windcarrier.

With a capacity up to 976.5 MW, Gennaker is to become the largest offshore wind farm in the German Baltic Sea to date. Located approximately 15 kilometres north of the Fischland-Darß-Zingst peninsula, the project area sits within a designated priority zone for offshore wind energy in the Mecklenburg-Vorpommern coastal sea. Skyborn secured the initial building permit for the Gennaker site in May 2019 and maintains site exclusivity for development. Gennaker is planned to be commissioned in 2028.

fncls.png
*Capacity as applied for, in the permit application for Gennaker offshore wind farm.

Contact
Bénédicte Bergeaud
Senior Director Global Corporate Affairs
b.bergeaud@skybornrenewables.com | +33 (6) 88 94 68 17

This press release and picture are available at https://www.skybornrenewables.com/articles/newsroom/Gennaker_PSA_major_contractors_signed

Hashtag: #Skyborn

The issuer is solely responsible for the content of this announcement.

About Skyborn Renewables

Skyborn is an accomplished offshore wind developer and operator with more than 20 years' experience, headquartered in Germany. The company's capabilities cover the entire offshore wind value chain, including greenfield development, project engineering and design, procurement, financing, corporate power purchase agreements, construction management and asset management. Skyborn is a portfolio company of New York based Global Infrastructure Partners (GIP), a leading infrastructure investor and part of Blackrock.

For more information, visit:
Follow us on LinkedIn:

Entrepreneurs & Leaders

How the EOR Model Works and What It Really Costs

If you have started hiring overseas, you have probably run into the term Employer of Record, or EOR. Most business o...

Why Smart Fleet Management Is Becoming a Business Essential

Spiralling fuel prices, shorter delivery windows and higher customer expectations have made managing a fleet of vehicl...

Fortifying the Perimeter: The Strategic Value of Galvanised Barbed Wire in Industrial Security

In an era where asset protection and risk mitigation are top priorities for businesses, perimeter security remains the...

Cardboard Boxes For Efficient Storage, Shipping, And Product Protection

Businesses across multiple industries depend on effective packaging solutions to protect products, improve logistics ope...

6 Best South Indian Restaurants in Melbourne

Few cuisines reward a bit of exploration quite like South Indian food. While butter chicken and naan tend to dominate ...

The Business Case for Reliable Liquid Waste Removal

Running a business comes with enough headaches without adding environmental violations, regulatory fines, or operational...

Using Headless CMS to Manage Sales Materials Across Multiple Business Units

Managing sales materials becomes more complex as a business grows across multiple departments, product lines, regions...

Why Corten Steel Is A Preferred Material For Durable And Weather-Resistant Applications

In environments where materials are exposed to the elements and long-term durability is essential, corten, commonly refe...

Why Businesses In Brisbane Are Investing In Structured Digital Marketing Agency

Working with a digital marketing agency in Brisbane has become an essential step for businesses aiming to strengthen t...

hacklink hack forum hacklink film izle hacklink online casinos australiaonwinonline casino australiatipobetligobetkuşadası escortfethiye escortbandar bolaجت بتmines gamebet808non gamstop casinoscasino sitesبازی پوپroyal reelsroyal reels casino australiaroyalreels.pokerbetpipoligobetligobet girişthe pokies net australiaz-library site oficialjojobetสล็อตสล็อตroyal reels casinograndpashabetstakebetpipo-ensonadres.comGalabetcasibompashagaming girişmeritkingmeritking